Primero Group, Bald Hill Lithium mine WA
Project Brief
- Testing and Commissioning
- Mobilize 2 technicians / Engineers
- Commencement – May 2017 to August 2017
Scope of work
- Cable Jointing and termination,
- Generator protection relay testing and others
- HV and LV Circuit Breaker Testing
- RMU Testing
- Busbar and Hipot Testing
- Transformer Testing
- Step and touch Testing
- Final Function checks
- Red and green lining of single line diagram
- Prepare ITP and final punch list
Outcome
- TCS not only completed project on time but within budget stipulated by ECM.
- All the testing and commissioning work was completed successfully.
Zero Harm - Mining Safety
The works were conducted without safety or environmental incident, and the site contact commended our workers on their professional and safe conduct and their commitment to the site’s safety principles.
Project Details
- Client : Primero Group
- Project : Bald Hill Lithium mine WA
- Contract Value : $75+